Westside Blvd. Widening Project Update February 24th

UPDATE: RIGHT-TURN LANE OPENED FOR EASTBOUND WESTSIDE BLVD TRAFFIC TO HEAD SOUTH ON NM 528; PROJECT SCHEDULED TO BE SUSPENDED AS OF MARCH 1, 2022
Update as of Thursday, February 24, 2022

CONTACT for questions and more information:
Patti Watson, 505-269-9691 cell; 505-245-3134 office; pattiw@cwastrategic.com

IMPORTANT NOTICE: The Westside Blvd Widening Project will go into suspension on Tuesday, March 1, 2022, for about three months so that the Water Authority can install a new raw water transmission pipeline along the south side of Westside Blvd. This work is being done now to minimize the impact homes and businesses along Westside by avoiding having to come back in and tear up newly installed asphalt paving. The Water Authority expects to complete construction in June 2022. After that, the City of Albuquerque will resume construction on this project and expects to complete it in about two months. You will automatically receive updates on the Water Authority project unless you unsubscribe. We apologize for the inconvenience and will work to get all construction in this area completed as soon as possible.

As of yesterday, Wednesday, Feb. 23, 2022, crews opened the dedicated right-hand turn for eastbound traffic on Westside Blvd to head southbound on NM 528.

The following traffic impacts are in place:

  • Westbound traffic on Westside Blvd is reduced to one lane between NM 528 and Golf Course Rd.
  • Eastbound traffic on Westside Blvd is reduced to one lane between Golf Course Rd and Grande Blvd. Eastbound traffic on Westside Blvd shifts to the south at Grande Blvd and has two lanes available as well as the dedicated right-hand turn lane to head southbound on NM 528.
  • Traffic on La Sierrita Rd and 7 Bar Loop Rd is able to turn right and head eastbound on Westside Blvd, but is NOT able to turn left and head westbound on Westside Blvd. Motorists can access westbound Westside Blvd by taking 7-Bar Loop Rd south to Driftwood Ave, heading west on Driftwood Ave, then north on Golf Course Rd. Westbound motorists on Westside Blvd can access La Sierrita or 7 Bar Loop Rd via Golf Course Rd south to Driftwood Ave, then east on Driftwood Ave to 7 Bar Loop Rd.

Regular work hours are Mon.-Fri., 6:30 a.m.-5 p.m., although the contractor may work longer hours or on weekends if needed. All construction is weather permitting and subject to change without notice.

Westside Blvd. Widening Project Update Feb. 16th

Image

Update as of Wednesday, February 16, 2022

Westside Blvd will shift to the north between Golf Course Rd and Grande Blvd as shown above.

The following traffic impacts will be in place:

  • Westbound traffic on Westside Blvd will be reduced to one lane between NM 528 and Golf Course Rd.
  • Eastbound traffic on Westside Blvd will be reduced to one lane between Golf Course Rd and Grande Blvd.
  • Eastbound traffic on Westside Blvd will shift to the south at Grande Blvd and have two lanes available.
  • Traffic on Grande Blvd, La Sierrita Rd and 7 Bar Loop Rd will be able to turn east or west on Westside Blvd, although there may be delays for traffic turning left.

Regular work hours are Mon.-Fri., 6:30 a.m.-5 p.m., although the contractor may work longer hours or on weekends if needed. All construction is weather permitting and subject to change without notice.

CONTACT for questions and more information:
Patti Watson, 505-269-9691 cell; 505-245-3134 office; pattiw@cwastrategic.com

Construction on Westside Blvd. for New Raw Water Transmission Pipeline

Image

Our HOA recently received the following communication from Patti Watson, President of CWA Strategic Communications, regarding additional construction on Westside Boulevard.

“Hello, my name is Patti Watson and I am president of CWA Strategic Communications. You may recognize my name because I have been handling communications for the City of Albuquerque’s Westside Boulevard Widening Project since construction began in May 2021. My firm has been sending out construction updates and we handle the project website — https://www.westsidewidening.com/.

I also work with the Albuquerque Bernalillo County Water Utility Authority (Water Authority). The Water Authority is working with Intel Corporation to build a new raw water transmission pipeline that will allow Intel to expand its operations in Rio Rancho, creating jobs and new economic development opportunities.

A portion of this pipeline, titled Bid Package 1—Westside Blvd on the map will be laid on the south side of Westside Blvd. from west of Golf Course Road to west of NM 528. The Water Authority is coordinating with the City of Albuquerque so that this portion of the pipeline can be built while the City’s project is still underway, before the roadway is repaved and/or the curb and sidewalk are removed and replaced.

Continue reading

ONC Hosting Virtual Lunch and Learn with NMDOT On I-25/Comanche Project This Thursday

The Office of Neighborhood Coordination (ONC) is hosting its first virtual Lunch and Learn of 2022 this Thursday, January 27 at 12:00 noon, and the public is invited to attend via Zoom. The topic is the I-25/Comanche Improvement Project and panelists will include staff from the New Mexico Department of Transportation (NMDOT) and key project contract staff, who will give a brief overview of the construction, answer questions about potential impacts on traffic and adjacent neighborhoods, and address other issues and questions. Neighborhood residents from directly adjacent neighborhoods will also be part of the panel, to ask more detailed questions and share concerns on behalf of their neighbors. The project is expected to have a citywide impact on traffic, so all neighborhoods and residents are encouraged to register for this webinar to learn as much as possible before the construction starts. The project website is available at: https://www.i25improved.com/
 
Register in advance for this webinar:
https://cabq.zoom.us/webinar/register/WN_-glpOPXURCKCoMCFsO8pVg
 After registering, you will receive a confirmation email containing information about joining the webinar.
 
If you cannot attend, please e-mail your questions to: vanessabaca@cabq.gov and they will be included as part of the panel discussion.

Westside Boulevard Project Update Jan. 13, 2022

Image

CONTACT for questions and more information:
Patti Watson, 505-269-9691 cell; 505-245-3134 office; pattiw@cwastrategic.com


NEW: Beginning Monday, Jan. 17,and lasting for about three weeks through Friday, Feb. 4, crews will work in the center of Westside Blvd from east of Golf Course Rd to west of NM 528.

During this closure, the following traffic impacts will be in place:

  • Westbound traffic on Westside Blvd will be reduced to one lane between NM 528 and Golf Course Rd
  • Westbound traffic will be able to turn left to access 7 Bar Loop Rd
  • Westbound traffic will not be able to turn left to access Sierrita Rd and should use 7 Bar Loop Rd to access Sierrita Rd
  • Eastbound traffic on Westside Blvd will be reduced to one lane between Golf Course Rd and NM 528
  • Eastbound traffic will not be able to turn left to access Grande Blvd, but can access Grande by turning left and heading north on NM 528, then turning left and heading west on 21st Ave SE to Grande Blvd

Regular work hours are Mon.-Fri., 6:30 a.m.-5 p.m., although the contractor may work longer hours or on weekends if needed. All construction is weather permitting and subject to change without notice.