Westside Boulevard Construction Update September 9th

Image

Westside Blvd. to have various Eastbound and Westbound lane closures and Golf Course Road to have various Northbound and Southbound right lane closures as crews continue to work on final project construction in September
Update as of Friday, Sept. 9, 2022

ONGOING
Crews are scheduled to continue working on lighting, paving, roadway striping, trail gravel, sidewalks and miscellaneous construction on this project, with construction expected to be substantially complete by the end of September.
 
Ongoing Traffic Impacts
• There are various eastbound and northbound lane closures on Westside Blvd. but at least one (1) lane will be open in each direction at all times.
 
• There are various right lane closures on northbound and southbound Golf Course Road north and south of Westside Blvd.
Regular work hours are Mon.-Fri., 6:30 a.m.-5 p.m., although the contractor may work longer hours or on weekends if needed. Saturday work is planned for the next few weeksAll construction is weather permitting and subject to change without notice.
CONTACTS for questions and concerns or to sign up for email updates on the project:
Patti Watson, 505-245-3134 office; 505-269-9691 cell; pattiw@cwastrategic.com
Ty Stevers, 505-245-3138 office; 505-417-9989 cell; tys@cwastrategic.com

Animal Welfare Department Hosting Adoption Clinic This Weekend

Image

The Animal Welfare Department needs your help. There are 800 pets in our city that need good homes, and our shelters are full. Animal Welfare is hosting an adoption clinic this weekend, Saturday, August 27 and Sunday, August 28, at the Eastside and Westside shelters, and the Everyday Adoption Center located in the Eubank PetSmart. The adoption fee is waived for all pets. Each adoption will include spay or neuter, a microchip, required vaccinations, and one free initial vet visit. For dogs, you will receive one free dog training class. This is a great opportunity to bring home a new furry friend. To learn more, visit: https://www.cabq.gov/pets/events/bases-are-loaded-at-animal-welfare-and-the-pets-need-a-home-run

Request Cockroach Control Through Water Utility Authority

Image

It’s officially monsoon season, and with all the much-needed rain and moisture come cockroaches. Cockroaches often take up residence in sanitary system manhole covers and breed, spreading to nearby residences. If you see cockroaches around a manhole cover, you can report this and request cockroach control from the Water Utility Authority. You can request this service online at: https://www.abcwua.org/sewer-system-cockroach-control/?fbclid=IwAR3gF_QcQhqw-LeqRKQ2APG2FeHc9aq6ArEGGlN6HFi15nMgUW3l42X6gGk

Independence Day Closures for City of Albuquerque

Image

Independence Day is Monday, July 4 and most City offices will be closed. The following services will still be offered on the holiday;

  • Trash and recycle pickup
  • 311 Community Call Center
  • City pools and golf courses
  • BioPark, Zoo and Aquarium

For more information, visit: https://www.cabq.gov/holiday/news/independence-day-holiday-information-2022

Westside Boulevard Construction Update June 24th

Image

CREWS TO CLOSE RIGHT LANE AND BIKE LANE OF EASTBOUND WESTSIDE BLVD BETWEEN BLACK ARROYO AND GOLF COURSE ROAD FOR JUST OVER ONE MONTH BEGINNING TUESDAY, JUNE 28 FOR CONSTRUCTION OF NEW RAW WATER TRANSMISSION PIPELINE
Update as of Friday, June 24, 2022 (NOTE: All work is weather permitting and subject to change without notice.)

Starting Tuesday, June 28, 2022 and lasting through about Thursday, July 28, 2022, the Water Authority and its contractor, New Mexico Underground, will close the right lane and bike lane for eastbound traffic/cyclists on Westside Blvd. from East Black Arroyo/Linear Park Trail to west of Golf Course Road for installation of a new 20-inch water pipeline.

One thru lane, one right turn lane and one left turn lane will remain open at the intersection of eastbound Westside Blvd and Golf Course Rd.
 
Motorists and bicyclists are asked to share the road in the construction zone where only one lane is available.
 
Additional construction phases will follow. Construction on this Raw Water Transmission Pipeline segment is expected to last through December 2022. Regular work hours are Monday-Friday 7am-5 pm although the contractor may work longer hours or on Sundays as needed.
 
STAY IN THE LOOP DURING CONSTRUCTION
Periodic updates will be sent throughout construction.  Please feel free to forward this notice to anyone you believe might be interested. Email pattiw@cwastrategic.com or tys@cwastrategic.com to sign up for project updates.
 
About the Raw Water Transmission Pipeline
Construction on this new 20-inch pipeline will provide “raw” or nonpotable water (not suitable for drinking) to support Intel’s multi-billion-dollar investment in upgrades and expansion at its Rio Rancho facility. Intel is an existing Water Authority customer and the planned upgrade is expected to create new jobs and economic development opportunities for our area. Several segments, or phases are included in this project, which is expected to last through the end of 2022 or early 2023.